23 NOV 23: A joint visit was conducted with the representatives from IA, IE, ZKDMC, and SEZMC to assess the progress at Dhabeji SEZ 23 NOV 23: A joint visit was conducted with the representatives from IA, IE, ZKDMC, and SEZMC to assess the progress at Dhabeji SEZ You Might Also Like A meeting was held on 16th February 2023 with the Transition Advisory Consultants of Khairpur SEZ February 17, 2023 A review meeting was held on 23rd July 2025 with consortium members Haidermota & Co., Exponent Engineering, and A.F Ferguson & Co., Chartered Accountants to discuss the progress of new industrial enclaves in Sindh. July 25, 2025 A Progress Review Meeting was held on the 10 MGD Water Supply Project for Dhabeji SEZ, focusing on overall completion and readiness for operations. December 16, 2025
A meeting was held on 16th February 2023 with the Transition Advisory Consultants of Khairpur SEZ February 17, 2023
A review meeting was held on 23rd July 2025 with consortium members Haidermota & Co., Exponent Engineering, and A.F Ferguson & Co., Chartered Accountants to discuss the progress of new industrial enclaves in Sindh. July 25, 2025
A Progress Review Meeting was held on the 10 MGD Water Supply Project for Dhabeji SEZ, focusing on overall completion and readiness for operations. December 16, 2025