Project review meeting for provision of 10 MGD water at door step of Dhabeji SEZ was held on 19th June 2025. The contractor provided updates on the construction progress. You Might Also Like A Progress Review Meeting held on 5th November 2025 with PwC (A.F. Ferguson), Haidermota & Co., and Exponent Engineering reviewed ongoing progress on the Sukkur Industrial Enclave. November 7, 2025 The Chief Minister directed the Board of Revenue (BoR) to hand over the possession of 1535 acres of land to DSEZ so that further process of its development of the zone could be started. July 21, 2020 Dhabeji Special Economic Zone – DSEZ: A #CPEC Priority Project, Transforming the Industrial landscape in the Region for brighter economic outlook of Pakistan. On 19th November 2024, a progress review meeting was held for the DSEZ. The meeting was attended by the developer, ZKBDMC, IA A.F Ferguson & Co., Chartered Accountants, and IE EA Engineering firm. November 21, 2024
A Progress Review Meeting held on 5th November 2025 with PwC (A.F. Ferguson), Haidermota & Co., and Exponent Engineering reviewed ongoing progress on the Sukkur Industrial Enclave. November 7, 2025
The Chief Minister directed the Board of Revenue (BoR) to hand over the possession of 1535 acres of land to DSEZ so that further process of its development of the zone could be started. July 21, 2020
Dhabeji Special Economic Zone – DSEZ: A #CPEC Priority Project, Transforming the Industrial landscape in the Region for brighter economic outlook of Pakistan. On 19th November 2024, a progress review meeting was held for the DSEZ. The meeting was attended by the developer, ZKBDMC, IA A.F Ferguson & Co., Chartered Accountants, and IE EA Engineering firm. November 21, 2024