A review meeting was held on 23rd July 2025 with consortium members Haidermota & Co., Exponent Engineering, and A.F Ferguson & Co., Chartered Accountants to discuss the progress of new industrial enclaves in Sindh. You Might Also Like A project review meeting and site visit for the provision of 10 MGD water at the doorstep of Dhabeji SEZ was held on 18th September 2025. The contractor provided updates on the construction progress. September 19, 2025 Project review meeting for provision of 10 MGD water at door step of Dhabeji SEZ was held on 28th August 2025 The contractor provided updates on the construction progress. August 29, 2025 Meeting with the Chinese delegates under the Chair of Secretary Investment, GoS March 27, 2019
A project review meeting and site visit for the provision of 10 MGD water at the doorstep of Dhabeji SEZ was held on 18th September 2025. The contractor provided updates on the construction progress. September 19, 2025
Project review meeting for provision of 10 MGD water at door step of Dhabeji SEZ was held on 28th August 2025 The contractor provided updates on the construction progress. August 29, 2025