Project review meeting for provision of 10 MGD water at door step of Dhabeji SEZ was held on 24th July 2025. The contractor provided updates on the construction progress. You Might Also Like SEZMC is striving to create an enabling environment to facilitate both domestic and foreign investors for economic growth in Sindh. A detailed progress review was carried out of Khairpur SEZ, Dhabeji SEZ, Marble City Karachi and other projects on 16th January, 2024 under the chair of CEO SEZMC. January 17, 2024 Providing an enabling environment for businesses is essential for Industrial growth. CEO, SEZMC while chairing the weekly progress review meeting November 7, 2023 A Progress Review Meeting was held on the 10 MGD Water Supply Project for Dhabeji SEZ, focusing on overall completion and readiness for operations. December 16, 2025
SEZMC is striving to create an enabling environment to facilitate both domestic and foreign investors for economic growth in Sindh. A detailed progress review was carried out of Khairpur SEZ, Dhabeji SEZ, Marble City Karachi and other projects on 16th January, 2024 under the chair of CEO SEZMC. January 17, 2024
Providing an enabling environment for businesses is essential for Industrial growth. CEO, SEZMC while chairing the weekly progress review meeting November 7, 2023
A Progress Review Meeting was held on the 10 MGD Water Supply Project for Dhabeji SEZ, focusing on overall completion and readiness for operations. December 16, 2025