A Progress Review Meeting was convened to assess the near-completion phase of the 10 MGD Water Supply Project for Dhabeji SEZ. You Might Also Like The Chief Minister directed the Board of Revenue (BoR) to hand over the possession of 1535 acres of land to DSEZ so that further process of its development of the zone could be started. July 21, 2020 The Weekly Progress Review Meeting assessed progress across SEZMC’s key projects, including #DhabejiSEZ, Khairpur Special Economic Zone. MCK Industrial Park, and AquaPark, emphasizing their combined importance in advancing industrial growth, enhancing infrastructure, and strengthening investor confidence across the region. January 28, 2026 05 September 2023 : Had a progress review meeting with ZKBDMC, discussing the progress at Dhabeji Special Economic Zone held at SEZMC Commitee room. September 6, 2023
The Chief Minister directed the Board of Revenue (BoR) to hand over the possession of 1535 acres of land to DSEZ so that further process of its development of the zone could be started. July 21, 2020
The Weekly Progress Review Meeting assessed progress across SEZMC’s key projects, including #DhabejiSEZ, Khairpur Special Economic Zone. MCK Industrial Park, and AquaPark, emphasizing their combined importance in advancing industrial growth, enhancing infrastructure, and strengthening investor confidence across the region. January 28, 2026
05 September 2023 : Had a progress review meeting with ZKBDMC, discussing the progress at Dhabeji Special Economic Zone held at SEZMC Commitee room. September 6, 2023