A Progress Review Meeting reviewed overall progress and recent updates on the 10 MGD Water Supply Project for Dhabeji SEZ, ensuring alignment on timelines and deliverables. You Might Also Like 20th June 2023 : Pre Bid Meeting on New Industrial Enclave held in committee room of SEZMC. June 22, 2023 Progress Review Meetings of Dhabeji Special Economic Zone – DSEZ was held today. The meeting attended by ZKBDMC , IA A.F Ferguson & Co., Chartered Accountants and IE EA engineering firm. April 16, 2025 Progress Review Meetings of Dhabeji Special Economic Zone – DSEZ was held on 22th April 2025. The meeting attended by ZKBDMC , IA A.F Ferguson & Co., Chartered Accountants and IE EA engineering firm. April 24, 2025
20th June 2023 : Pre Bid Meeting on New Industrial Enclave held in committee room of SEZMC. June 22, 2023
Progress Review Meetings of Dhabeji Special Economic Zone – DSEZ was held today. The meeting attended by ZKBDMC , IA A.F Ferguson & Co., Chartered Accountants and IE EA engineering firm. April 16, 2025
Progress Review Meetings of Dhabeji Special Economic Zone – DSEZ was held on 22th April 2025. The meeting attended by ZKBDMC , IA A.F Ferguson & Co., Chartered Accountants and IE EA engineering firm. April 24, 2025