A review meeting was held on 15th May 2025 to assess progress on the provision of 10 MGD water to Dhabeji SEZ. The contractor shared construction updates and timelines. You Might Also Like 2nd August 2023 : Had a progress review meeting with ZKBDMC, discussing the progress at Dhabeji Special Economic Zone held at SEZMC Commitee room. August 2, 2023 Progress Review Meeting of all Projects of SEZMC held on 11th June 2024, chaired by CFO SEZMC, progress discussed about all projects. June 13, 2024 Special Economic Zones, a key component of China Pakistan Economic Corridor (CPEC), are expected to usher in a new era of industrial development and economic growth in the country in the days ahead. April 13, 2022
2nd August 2023 : Had a progress review meeting with ZKBDMC, discussing the progress at Dhabeji Special Economic Zone held at SEZMC Commitee room. August 2, 2023
Progress Review Meeting of all Projects of SEZMC held on 11th June 2024, chaired by CFO SEZMC, progress discussed about all projects. June 13, 2024
Special Economic Zones, a key component of China Pakistan Economic Corridor (CPEC), are expected to usher in a new era of industrial development and economic growth in the country in the days ahead. April 13, 2022