Dhabeji SEZ, a vital CPEC project in Sindh, takes a leap forward with the land lease agreement signing. Led by the Sindh Govt. & developed under PPP’s vision, it aims to attract investment to Pakistan. Offering a plug & play platform for investors. You Might Also Like Doing Business (DB) ranks economies across the world annually on the basis of 10 comprehensive areas in the life cycle of a business. February 4, 2020 GoS is committed to creating a plug & play environment for local & international investors. In this regard weekly progress review meeting was held on 7th May 2024 led by CEO SEZMC, progress discussed about all projects. May 9, 2024 Project review meeting for provision of 10 MGD water at door step of Dhabeji SEZ was held on 19th June 2025. The contractor provided updates on the construction progress. June 20, 2025
Doing Business (DB) ranks economies across the world annually on the basis of 10 comprehensive areas in the life cycle of a business. February 4, 2020
GoS is committed to creating a plug & play environment for local & international investors. In this regard weekly progress review meeting was held on 7th May 2024 led by CEO SEZMC, progress discussed about all projects. May 9, 2024
Project review meeting for provision of 10 MGD water at door step of Dhabeji SEZ was held on 19th June 2025. The contractor provided updates on the construction progress. June 20, 2025