Progress Review Meeting with concessionaire Of Dhabeji SEZ held on 16th April 2024 meeting attendant by developer ZKBDMC, IA A.F Ferguson & Co., Chartered Accountants and IE EA Engg, meeting was Chaired by CEO SEZMC You Might Also Like The Special Economic Zones (SEZ)’s Approval Committee (AC) has referred zone application of Dhabeji SEZ for consideration of the Board of Approvals (BoA) on 14th August 2020, Thursday. August 14, 2020 Technical design study will be completed by January 2024 for provision of 10 MGD Water at the doorstep of Dhabeji SEZ. The progress of ADP scheme reviewed during a meeting held today 29th December 2023. The meeting was attended by senior officials of SEZMC, KWSC, consultants January 1, 2024 Weekly Progress Review Meeting held today, covering progress across initiatives, and reinforcing timely execution. April 15, 2026
The Special Economic Zones (SEZ)’s Approval Committee (AC) has referred zone application of Dhabeji SEZ for consideration of the Board of Approvals (BoA) on 14th August 2020, Thursday. August 14, 2020
Technical design study will be completed by January 2024 for provision of 10 MGD Water at the doorstep of Dhabeji SEZ. The progress of ADP scheme reviewed during a meeting held today 29th December 2023. The meeting was attended by senior officials of SEZMC, KWSC, consultants January 1, 2024
Weekly Progress Review Meeting held today, covering progress across initiatives, and reinforcing timely execution. April 15, 2026