Progress Review Meetings of New Industrial Enclaves in Hyderabad, Sukkur and SBA was held today. The meeting attended by consortium members Exponent Engg, HMCO and A.F Ferguson & Co., Chartered Accountants You Might Also Like Site Visit of Bin Qasim Industrial Park June 19, 2019 Technical design study will be completed by January 2024 for provision of 10 MGD Water at the doorstep of Dhabeji SEZ. The progress of ADP scheme reviewed during a meeting held today 29th December 2023. The meeting was attended by senior officials of SEZMC, KWSC, consultants January 1, 2024 20th Februrary 2024: Progress review meeting with Consultant EY along with others to discuss the progress at Marble City and Khairpur SEZ held at SEZMC Committee room. February 21, 2024
Technical design study will be completed by January 2024 for provision of 10 MGD Water at the doorstep of Dhabeji SEZ. The progress of ADP scheme reviewed during a meeting held today 29th December 2023. The meeting was attended by senior officials of SEZMC, KWSC, consultants January 1, 2024
20th Februrary 2024: Progress review meeting with Consultant EY along with others to discuss the progress at Marble City and Khairpur SEZ held at SEZMC Committee room. February 21, 2024