Weekly Progress Review Meeting focused on updates across all projects and maintaining coordination, with emphasis on progress, alignment, and timely execution. You Might Also Like On 16th April 2026, a weekly progress review meeting was convened to evaluate advancements on the 10 MGD Water Supply Project at Dhabeji SEZ, with contractors presenting key updates as the project moves towards completion. April 20, 2026 Progress Review Meetings was held on 24th december 2024. During the meeting, progress on all projects was discussed and reviewed. December 26, 2024 7th May 2025 – Site visit to Dhabeji SEZ for 10 MGD water supply alongwith with Consultant EA and Contractor Hasaas & Kainaat (JV). May 9, 2025
On 16th April 2026, a weekly progress review meeting was convened to evaluate advancements on the 10 MGD Water Supply Project at Dhabeji SEZ, with contractors presenting key updates as the project moves towards completion. April 20, 2026
Progress Review Meetings was held on 24th december 2024. During the meeting, progress on all projects was discussed and reviewed. December 26, 2024
7th May 2025 – Site visit to Dhabeji SEZ for 10 MGD water supply alongwith with Consultant EA and Contractor Hasaas & Kainaat (JV). May 9, 2025