On 16th April 2026, a weekly progress review meeting was convened to evaluate advancements on the 10 MGD Water Supply Project at Dhabeji SEZ, with contractors presenting key updates as the project moves towards completion. You Might Also Like 31st May 2023: Meeting with NTDC regarding progress update and timelines of 220kV Grid June 1, 2023 DSEZ will emerge as the center of foreign investment and innovation. DSEZ progress review meeting with ZKBDMC was held today. The meeting was chaired by CEO SEZMC and was attended by the IE, IA and others. The importance of attracting foreign investment was discussed and agreed. November 14, 2023 A review meeting was held on 8th October with consortium members Haidermota & Co., Exponent Engineering, and A.F Ferguson & Co., Chartered Accountants to discuss the progress of new industrial enclaves in Sindh. October 8, 2025
DSEZ will emerge as the center of foreign investment and innovation. DSEZ progress review meeting with ZKBDMC was held today. The meeting was chaired by CEO SEZMC and was attended by the IE, IA and others. The importance of attracting foreign investment was discussed and agreed. November 14, 2023
A review meeting was held on 8th October with consortium members Haidermota & Co., Exponent Engineering, and A.F Ferguson & Co., Chartered Accountants to discuss the progress of new industrial enclaves in Sindh. October 8, 2025